Message Board

Topic: Builders at Clydesdale Rd Post A Reply | Post A New Message
Message Posted: 5/9/2019
By: Jennifer Gunnet, Twp. Mgr.

A follow-up was done. The materials were the contractor for Columbia Gas, the new homes contractor and the contractor installing the sidewalk. All have been cleaned up.
Message Posted: 5/9/2019
By: S. Mease

Can you please do another follow-up?
Message Posted: 5/6/2019
By: Jennifer Gunnet, Twp. Mgr.

Thank you for the information. We will contact them.
Message Posted: 5/5/2019
By: S Mease

The builders left all their driveway gravel piles on Clydesdale Rd which has now been washed out from rain and run down into the road and in the storm drains. Please check this out